We are excited about these two upcoming projects and thank you for your assistance as we continue fulfilling our mission, goals and objectives. Below is the schedules for the projects.

Pavement Restoration Project Schedule:
.
May 2-3, 2018: Terminal Parking Lot – No tenants and cars permitted beginning May 1st, 2018 at 10pm.
May 2, 2018: Runway – NOTAM issued. Runway will be closed and will reopen May 3, 2018. When the runway reopens, it will be partially grooved until grooving is complete at a later date. The final grooving date has not been determined. Another runway closure date for this work is forthcoming.
May 3-4, 2018: AO1/AO2. No aircraft and tenants permitted.
May 3-5, 2018: Areas A, B, C. No aircraft and tenants permitted.
May 5-6, 2018: Area D. No aircraft and tenants permitted.
May 6-7, 2018: Area E (cuts off T-hangar access). No aircraft and tenants permitted.
May 8-9, 2018: Area F. No aircraft and tenants permitted.
May 9-11, 2018: Tudor Pad. No aircraft and tenants permitted.
May 14-17, 2018: Parking lot and Airfield painting (all non-movement areas). Contractor shall give priority to aircraft traffic.